Temporary Sewer Bypass Installation and Upcoming 18th Street Closure
November 2, 2017
November 6 – November 22 the contractor will install the sewer bypass system. The temporary bypass pipes will be placed above ground, except where it crosses a road or driveway. In that circumstance, a small trench will be excavated, and the piping will be buried. The bypass pump will be located in the westbound lane of 18th Street, just east of Osborn Avenue.
o The pumping operation will begin on November 27.
o During the bypass installation, motorists and area residents should watch for intermittent lane closures in the area of work.